Khmelnytskyy Nuclear Power Plant

Khmelnytskyy Plant Operating History

Scope of DOE Activities

Accomplishments

Plant Manager: Mykola Dudchenko
Chief Engineer: Volodymyr Sofiyuk
Utility: Energoatom
Telephone No.: 380-3848-33350
Fax: 380-3848-33360


Reactor Model Net Output Initial Criticality Commercial Start
Unit 1 VVER-1000 950 MWe 12/1987 8/1988
Unit 2 VVER-1000 950 MWe NA NA
Unit 3 VVER-1000 950 MWe NA NA
Unit 4 VVER-1000 950 MWe Under construction
Khmelnytskyy Units 1-4
Neteshin, Khmelnytskyy Ukraine
Pressurized Water Reactor (PWR)
Utility: Derzhkomatom
Reactor Supplier: Mintyazhmash
Steam Generator Supplier: Leningradsky Metalichesky Zavod
Architecture: Atomenergoproject
Construction: Ministry of Power Stations


^top

----------